Construction Updates

Monday, June 10, 2019

Havlerson Elementary
Week ending 6/14/19

  • Site demo to begin early in the week
  • Site work begins following demo clean up
  • Steel joists to begin

               
Cutting gym walls prior to demo                      

Hammer Complex 
Week ending 6/14/19

  • Seat wall foundations to begin
  • Exterior slabs South of retaining wall to be poured
  • Football/Soccer turf to begin install

    
Foundation work for dugout                      Masonry Walls at Grandstand

Week ending 6/7/19

  • Masonry Walls at Grandstand going up
  • Football/Soccer field continues to be prepped for turf
  • Plumbing Rough-in at concession stand complete
  • Setting pre-cast panels at field house
  • Football/Soccor field prep for turf continued
  • Grading work around completed Hammer sidewalk

Week ending 6/7/19

  • Finish setting pre-cast panels at field house
  • Retaining wall to be back-filled
  • Masonry walls at grandstand continues
  • Underground plumbing rough-in at Grandstand
  • Begin dugout foundation work

Fieldhouse pre-cast work                                                            Masonry Walls at Grandstand

                       

Albert Lea High School HVAC and Pool Locker Room Renovations
Week 5/31-6/7

  • Finish floor slab in locker rooms
  • Masonry work to begin

       

Halverson Elementary
5/31-6/7

  • Interior Demo work continues
  • Mass demo to begin on 6/3 

   

 

 

 

 

 

 

 


Halverson Elementary
5/17/19

  • Pre-construction activities taking place
  • Construction to begin upon end of school year
  • Groundbreaking Ceremony May 23rd at 3:00pm

Albert Lea High School HVAC and Pool Locker Room Renovations
5/17/19

  • HVAC Gym Cooling operational
  • Slab for Locker room ready to pour

5/24/19

  • Floor slab to be poured
  • Masonry to follor floor pour

Hammer Complex
5/17/19

  • Footing and foundation work at Grandstand continues
  • Underground utility service connections made at street
  • Football field being prepped and drainage installed
  • Pedestrian sidewalk from Hammer complex to High School along Hammer road near completion
  • Softball/Baseball concessions building foundation complete
  • Underground plumbing at Fieldhouse
  • Masonry bearing walls at Fieldhouse

 5/24/19

  • Erection crane for pre-cast to site
  • Retaining wall to be back-filled
  • Masonry at Grandstand
  • Underground plumbing rough-in at Grandstand
  • Back-fill at concessions and Grandstand

Aerial of Football/Soccerr Field excavation

 

Aerial of Soccer Field grading (NW corner of site) and current/future parking area

 

 

 

 

 

 

 
5/10/19

  • Footing and foundation work at Grandstand
  • Underground utility service connections to be made
  • Pedestrian sidewalk from Hammer complex to High School along Hammer road to be poured

5/3/19

  • Fieldhouse footings complete
  • Grandstand aggregate piers to be placed
  • Retaining wall at Grandstand near completion
  • Retaining wall to be backfilled
  • Interior masonry footings at Fieldhouse
  • Interior masonry walls to begin at Fieldhouse
  • Turf soccer/football field work continues

 

4/22/19

  •  Footing and foundation work continues
  •  Retaining wall work continues
  •  Foundation wall pours to begin at fieldhouse
  •  Groundbreaking Ceremony was held

 

4/16/19

  • Footing and foundation work continues
  • Retaining wall work continues
  • Foundation wall pours to begin at fieldhouse

  • Plumbing underground rough-in work in locker room to continue
  • HVAC Control work continues
  • Plumbing work in locker room to continues
  • Foundation wall pours to begin at fieldhouse

 

4/3/19
Here you can see the bus garage being prepped before it was relocated. The next photo shows the grandstand retaining wall footing. At the high school, the existing floor slab was removed in the pool locker room and heat pumps were installed for gymnasium cooling. Meanwhile at Halverson, lots of pre-construction activities are taking place as they prepare for construction beginning at the end of the school year!

 

2/21/19
District residents have noticed that the Jim Gustafson Memorial has been taken down. As this plan illustrates, the plaque will be placed on our new stadium wall, with the bricks re-etched with donors names on them.