2/21/19 District residents have noticed that the Jim Gustafson Memorial has been taken down. As this plan illustrates, the plaque will be placed on our new stadium wall, with the bricks re-etched with donors names on them.

4/3/19 Here you can see the bus garage being prepped before it was relocated. The next photo shows the grandstand retaining wall footing. At the high school, the existing floor slab was removed in the pool locker room and heat pumps were installed for gymnasium cooling. Meanwhile at Halverson, lots of pre-construction activities are taking place as they prepare for construction beginning at the end of the school year!

 

4/16/19

  • Footing and foundation work continues
  • Retaining wall work continues
  • Foundation wall pours to begin at fieldhouse

  • Plumbing underground rough-in work in locker room to continue
  • HVAC Control work continues
  • Plumbing work in locker room to continues
  • Foundation wall pours to begin at fieldhouse